X can do a piece of work in 5 hours, Y in 9 hours, and Z in 15 hours. If Z could work with them for 1 hour only, the time taken by X and Y together to complete the work is:
a) 2 hours
b) 2.5 hours
c) 3 hours
d) 3.5 hours