Answer:

The answer is Work Package.

Explanation:

Work Package is the work component at the lowest level of the work breakdown structure(WBS), for which cost and duration can be estimated and managed; beyond this level, further decomposition will not be done.

Work packages are the primary input to identify activities' process. They are planned by way of identifying activities under them.