Respuesta :
Answer: feed back control
Explanation:
Communication in control is very important, and for you to ascertain that a control process is successful,is by having a good feedback, it is not all times that we get a positive feedback but feedback is what completes the process of control, without feedback we can't know if the process failed or not, so feedback is very important that is why after controlling a process , a feedback occurs to ascertain if the control process was completed.
The control that takes place after the completion of an action is the Feedback control.
Feedback control:
- Refers to adjusting a project based on activities that have already happened in the project.
Feedback control therefore relies on actions to have been completed to work and so only takes place after that action has been completed unlike a feedforward control which takes place before the action.
In conclusion, option B is correct.