contestada

The following data for the telephone company pertain to the production of 450 rolls of telephone wire during June. Selected items are omitted because the costing records were lost in a windstorm.

Direct Materials (All materials purchased were used)

Standard cost per roll: a pounds at $4.00 per pound

Total actual cost: b pounds costing $9600.

Standard cost allowed for units produced was $9000

Materials price variance: c

Materials efficiency variance was $80 unfavorable.

Direct Manufacturing Labor

Standard cost is 3 hours per roll at $8.00 per hour

Actual cost per hour was $8.25

Total actual cost: d

Labor price variance: e

Labor efficiency variance was $400 unfavorable.

Required:

Compute the missing elements in the report represented by the lettereditems.

Respuesta :

Answer:

a. Standard Quantity= 2250

b. Actual Quantity= 2570

c. Material Price Variance= 680 Fav

d. Total actual cost $ 10725

e. Labor price variance  $ 325

Explanation:

Telephone Company

Direct Materials (All materials purchased were used)

Standard cost per roll: a  2250 pounds at $4.00 per pound

Total actual cost: b  2570 pounds costing $9600.

Actual unit Price = $ 9600/2570= $ 3.75

Standard cost allowed for units produced was $9000

Material Price Variance= (Actual Price * Actual Quantity)- (Standard Price * Actual Quantity)

Material Price Variance= (3.75*2570)- 4*2570= 9600- 10280= 680 Fav

Material yield variance is also called Material Efficiency variance = (Actual unit usage - Standard unit usage) x Standard cost per unit

$ 80= (Actual units- $ 9000/$4) *$4

$80 *4= (Actual units- 2250)

320+ 2250= Actual Units

Actual Units= 2570

Materials efficiency variance was $80 unfavorable.

Direct Manufacturing Labor

Standard cost is 3 hours per roll at $8.00 per hour

Actual cost per hour was $8.25

Total actual cost:  1300 hours * $8.25= $ 10725

Labor price variance: (actual hours* actual rate)- (actual hours * standard rate)

Labor price variance = $ 10725- 1300*8=  $ 10725-$ 10400= $ 325

Labor efficiency variance was $400 unfavorable= Standard Hours *Standard Rate - Actual Hours *Standard Rate

400= (3*450*8)-(Actual Hours *8)

10800-400= (Actual Hours *8)

(Actual Hours) =10400/8= 1300