Crane Company applies overhead on the basis of machine hours. Given the following data, compute overhead applied and the under- or overapplication of overhead for the period:

Estimated annual overhead cost $1700000
Actual annual overhead cost $1675000
Estimated machine hours 400000
Actual machine hours 390000


$1657500 applied and $17500 overapplied
$1657500 applied and $17500 underapplied
$1675000 applied and neither under-nor overapplied
$1700000 applied and $17500 overapplied