In some situations, an activity cannot start until a certain time after the end of its predecessor, and the waiting period is commonly known as a finish to start (FS).
What is the finish to start (FS)?
- Finish to Start (FS)—The previous leader must come to an end before the successor can begin.
- Start to Start (SS)—The predecessor starts before the successor.
- Finish to Finish (FF)—The predecessor comes to an end before the successor can come to an end.
- In some cases, an activity cannot begin until a certain time after the conclusion of its predecessor, and this period is commonly referred to as a finish to start (FS).
- This is the most common scenario, and in the absence of any other criteria, all tasks may be dependent on this dependency in order to produce a working schedule.
- "Supper begins when the cooking is finished," for example.
- "Concrete pouring begins after the forms are constructed."
Therefore, in some situations, an activity cannot start until a certain time after the end of its predecessor, and the waiting period is commonly known as a finish to start (FS).
Know more about the finish to start (FS) here:
https://brainly.com/question/28257320